Executive Summary
OCS Indonesia delivers facilities management for a leading hyperscale data centre operator in Indonesia, with a 99.93% SLA score reported against a 98% target in July.
The campus spans approximately 65,000 square metres and is designed to support up to 75 MW of IT capacity. OCS combined Facilities Management Agent (FMA) governance of critical systems with building management services in one operating model, mobilised within a one-month implementation period.
Data Centre Performance in Numbers
Figures from the July reporting period show how FMA governance and building management performed at an Indonesian hyperscale data centre.
-
99.93%
FMA SLA Score Against 98% Target
-
99%
Workforce Hours Achieved, July Reporting Period
-
100%
Monitored System Availability, Data Halls
The Challenge
As a newly operational hyperscale data centre, the customer needed a partner able to govern critical facility activities, coordinate specialist maintenance suppliers, manage building services and provide clear evidence of performance through structured reporting and service-level controls.
The operating model also had to support rapid growth and stringent uptime expectations, with disciplined procedures, safe working practices and consistent standards across critical and non-critical areas. It had to be fully operational within an aggressive implementation timeline and protect availability and environmental conditions in mission-critical areas.
The Solution
OCS Indonesia mobilised its operating model within a one-month implementation period.
A Facilities Management Agent (FMA) team oversees critical systems day to day, monitoring cooling, electrical, power backup, control and fire-suppression systems, identifying abnormalities and coordinating incidents. OCS governs preventive maintenance by specialist suppliers rather than acting as sole executor, validating schedules, coordinating access, confirming documentation, tracking execution and escalating deviations.
Cleaning, gardening, facade cleaning, building maintenance technicians and security work under one building management governance structure. SLA and SLG measures, daily and monthly reporting and root-cause analysis turn field activity into management information.
The FMA SLA score was 99.93% against a 98% target in the July reporting period.
Best Outcomes
The integrated FMA and building management model protects critical operations, improves service control and generates information for better management decisions. The figures below come from specific reporting periods and are not guarantees of future results.